For Swiss public administrations and for suppliers delivering to the public sector
HERMES is the project management method of the Swiss federal administration, also used by many cantons, municipalities and public companies. I am HERMES Advanced certified, the level designed for project managers. Depending on your position in the project, I can support you in two ways.
User organisation (public client)
Supplier (developer)
Operator
For public administrations: external project manager
HERMES requires the project manager to belong to the user organisation and to represent its interests alone, but the role can be filled by an external person. In this role, I run the project on your behalf: project management plan, project status reports, preparing the sponsor’s decisions at milestones, managing suppliers.
If the project goes off track, I also help you regain control: review the results, bring decisions back to the right level, replan the phases. See project recovery.
For suppliers: delivering in a HERMES project
Are you delivering a solution, a system or a service to a public client that runs its project according to HERMES? Your client has its own project manager. On the supplier side, as sub-project manager or delivery lead, I make sure your results, deadlines and reports match what the client expects at each milestone:
- understand the HERMES requirements of the tender and of the client, and structure your delivery plan accordingly;
- deliver the expected results at the right time and in the expected form;
- bridge your internal method and the client’s project organisation, especially for foreign suppliers. See external project manager.
To avoid any conflict of interest, I never hold both roles in the same project.
Why it matters
In a HERMES project, the public client makes its decisions at milestones, based on clearly defined results: project management plan, project status reports, decision documents. A supplier unfamiliar with this framework loses time in back and forth, and the project falls behind.
What I bring
My HERMES Advanced certification complements my PMP® and PMI-ACP® certifications: HERMES for the framework of the Swiss administration, PMI for internationally recognised project management techniques, agile for developing the solutions.
My experience comes from government biometric identity programmes delivered in 7 countries, on the supplier side: ministries as clients, steering committees, stage approvals and formal acceptance. The HERMES Advanced certification gives me the framework and vocabulary of the Swiss administration to apply this experience here.
- Certified HERMES Advanced, PMP®, PMI-ACP®, Lean Six Sigma Black Belt
- EPFL engineer
- French, German, English
Frequently asked questions
Can the project manager be external?
Yes. HERMES attaches the project manager to the user organisation, whose interests they represent exclusively. The organisation can, however, bring in an external person for this role. The project manager should not come from the supplier or from the operator of the solution.
What role can the supplier play in the project organisation?
The supplier (the “developer” in HERMES) develops or supplies the solution and handles its integration. Its managers can take on the role of sub-project manager, leading part of the project on behalf of the client’s project manager.
Which roles are essential in a HERMES project?
Three roles must always be filled on the user organisation side: project sponsor, project manager and user representative. In a small project, the project manager and the user representative can be the same person.
Who decides what between the project sponsor and the project manager?
The sponsor steers the project: they are responsible for the objectives and decide at milestones, for example to release the next phase. The project manager runs the project: they make decisions on the results and report regularly to the sponsor. The execution order is the binding agreement between the two.
How does acceptance of the solution work?
Acceptance takes place between the project sponsor, the supplier and the operator of the solution. It is a key moment for the supplier: the expected results must be ready and match what was agreed.
Is HERMES compatible with an agile approach?
Yes. Since the 2022 edition, the solution can be developed in a traditional, agile or hybrid way, within the same steering framework. In agile mode, the development team is part of the project organisation and organises itself. The project manager does not interfere with this organisation: they work through the user representative, who also represents the team.
How do you combine HERMES and agile?
I am certified PMI-ACP® and Professional Scrum Master, and I have been Product Owner of a product development team. So I know both sides: the steering framework HERMES sets at project level, with its milestones and decisions, and the daily work of an agile team, with its sprints, backlog and reviews. My role is to hold the two together: let the team organise itself, while giving the sponsor the information needed to decide at milestones.
How do you combine HERMES and PMI standards?
They complement each other. HERMES defines what must be produced and decided in a Swiss public administration project: roles, phases, milestones and results. PMI standards, which I apply as a PMP® certified project manager, provide the techniques to get there: planning, risk, stakeholder and cost management, progress tracking. I use HERMES as the framework and PMI practices as tools, without duplicating documents.